13 May Continued Demo
5/13, The wall is out, the pad is set, and footing and drainage lines beginning to take shape. In good shape to start setting formwork and drainage next week, right on schedule.
School Fees have been paid and we’re awaiting final documents. With two 1/2 weeks left to pour concrete we’re still in good position. If we don’t have it by middle of next week, we’ll start banging on more doors.
Good meeting w Joe and Mena Wednesday. Monica and Beatriz are reworking the Bathroom 1 layouts and setting up the same drawing and spec package for the kids bath.
Sorry, the comment form is closed at this time.